Preparing a Sub-base

Preparing a Sub-base
Gardening Guides Editorial 31 July 2026

Sunken slabs, rocking paving, cracked joints and weeds growing through are nearly always failures of what lies beneath rather than of the surface itself. The sub-base is the part nobody sees and the part that determines how long the job lasts.

How deep to excavate

Work back from the finished level, adding up the layers.

For a pedestrian path or patio: around a hundred millimetres of compacted sub-base, twenty-five to forty millimetres of bedding mortar, and the thickness of the paving itself. That usually means excavating a hundred and eighty to two hundred and fifty millimetres.

For a drive or anywhere vehicles will run: a hundred and fifty millimetres of sub-base as a minimum, and two hundred on soft ground.

Excavate a little wider than the paved area on each side so edge restraints can be bedded properly.

Remove everything soft

Dig out topsoil, turf, roots and any soft or organic material entirely. Organic matter rots and the surface above it sinks.

Reach a firm subsoil base. Where you meet soft spots, dig them out and fill with additional sub-base material rather than leaving them.

Check the ground is firm by walking or wheeling a loaded barrow over it. Anything that moves needs excavating further.

What material to use

MOT Type 1 granular sub-base is the standard, and it works because it contains a range of particle sizes from around forty millimetres down to fines. The small particles fill the voids between the large ones, which is what allows it to compact into a dense stable layer.

Do not use single-sized gravel or pea shingle, which cannot lock together and will always move.

Where drainage through the surface is intended, a clean angular material without fines is used instead, and the design is different.

Crushed concrete is an acceptable and cheaper recycled alternative for domestic work.

Compacting is the critical step

Compact in layers of no more than seventy-five to a hundred millimetres. This is the point most often ignored and the cause of most later settlement.

A single deep layer cannot be compacted properly however long you run the machine over it. The lower part stays loose and settles later.

Use a vibrating plate compactor, hired for the day, running over each layer several times in different directions.

Lightly dampening dry material helps it compact, though it should not be saturated.

The finished surface should feel solid underfoot with no movement and no loose material.

Levels and falls

Set the levels before you start, using pegs and a string line or a laser level.

Build the fall into the sub-base rather than trying to correct it in the bedding layer, since a thick wedge of mortar behind one edge is a weak point.

A fall of about one in eighty is right for most paving, directing water away from any building.

The finished paving must sit at least a hundred and fifty millimetres below the damp-proof course. This is the error that causes damp inside a house and is expensive to correct.

Where a surface must be higher, use a drainage channel and a gap against the wall rather than butting paving to it.

Geotextile membrane

A layer between the subsoil and the sub-base is worth including on soft or clay ground.

It separates the two, preventing the sub-base being pushed down into soft subsoil and the subsoil migrating upwards, which is a common cause of long-term settlement.

It is not a weed membrane and does not replace one.

Where the material goes

Excavated spoil is a substantial volume and needs somewhere to go. Allow for a skip or a grab lorry, since a patio excavation produces more material than people expect.

Order sub-base by weight rather than volume and allow a margin, since it consolidates considerably when compacted.

Working safely

Slabs and bulk bags are heavy. Get help, use a sack truck, and lift with your knees rather than your back.

Check for buried services before excavating, and look up for overhead lines.

Getting the levels right first

Set out the finished level before excavating, using pegs driven to the intended height and a string line between them.

Work back from fixed points that cannot change: the damp-proof course, a door threshold, an existing path or a manhole cover that must remain accessible.

Getting this wrong is discovered at the end of the job when the paving is too high or the fall runs the wrong way, and it means starting again.